PGE tree removal in Forest Park approved after City Council rejection
A hearings officer cleared a plan to cut 393 trees, triggering a new appeal deadline for conservation groups.
By Marco Ortega ·

Hearings Officer Marisha Childs approved Portland General Electric’s revised plan to remove 393 trees from Forest Park on Friday. The ruling permits the utility to cut 375 living trees and 18 dead ones on about 5 acres of the park. It also allows the permanent filling of two wetlands and disturbance to 4.7 acres of natural resource land. The decision reverses a unanimous City Council vote from last year that rejected the original proposal.
The project, called the Harborton Reliability Project, involves rewiring a 1970s transmission line and adding a second line within the utility’s existing right of way. PGE states the upgrade is necessary to prevent outages in North and Northwest Portland. The company also argues the work helps ease transmission bottlenecks to support Oregon’s clean energy mandates. Childs agreed with city staff that no feasible alternative route would cause less environmental damage.
The approval is contingent on a $5.5 million environmental mitigation fund. This amount is $3.1 million higher than PGE’s initial offer. Under a mediation agreement reached in July, the city and the utility agreed to this funding structure. Childs required that a large portion of the money be spent in the specific area where construction will occur. PGE must also conduct wildlife surveys and follow timing restrictions to protect amphibians before work begins.
Conservation groups have criticized the process as a backroom deal. The Forest Park Conservancy, the Bird Alliance of Oregon, and the Forest Park Neighborhood Association participated in mediation after PGE placed its appeal before the Oregon Land Use Board of Appeals on hold. Childs rejected arguments that the agreement should be voided due to backdoor dealings. She stated those issues were outside the scope of her approval criteria.
Carole Hardy, a board member of the Forest Park Conservancy, said the decision was not a surprise. She expects the group to appeal the ruling to the City Council. Bob Weinstein, a Northwest District activist, called the outcome a win for PGE and a loss for the park. PGE spokesperson Andrea Platt described the decision as a thorough and reasoned review of the evidence.
Any appeal must be filed with the City Council by Dec. 4. The council previously rejected the plan after receiving thousands of written and in-person testimonies. This time, councilors will weigh a plan backed by city staff, accompanied by higher mitigation funds, and cleared by the hearings officer. The decision timeline follows a public hearing held Oct. 14 and a record closure on Nov. 4.