Columbia River bridge: Single bid from Kiewit-led team sparks cost worries

Lawmakers question accountability as the I-5 replacement project moves forward with a design firm that has faced recent budget and schedule issues in Oregon.

By Bianca Shevchenko ·

Illustration for: Columbia River bridge: Single bid from Kiewit-led team sparks cost worries
Illustration generated for this article, not a news photograph.

The Interstate Bridge Replacement Program received only one design bid for the new I-5 span across the Columbia River. The proposal came from Columbia River Constructors, a joint venture that includes Kiewit Engineering Group, Guy F. Atkinson Construction, and Traylor Bros. Inc. Kiewit will lead the effort.

Kiewit is a subsidiary of the Nebraska-based Kiewit Corp and currently builds the Interstate 205 Abernathy Bridge in Oregon City. That project is running more than two years behind schedule. Its cost estimate has risen to $800 million, a figure that is more than three times the $250 million price tag set in 2018, according to KGW.

The firm also designed the Hood River-White Salmon Bridge Replacement Project, which it began in 2024. The price for that work has doubled to more than $1.2 billion. Joe Cortright, an economist at the Portland-based think tank City Observatory, said the increase resulted partly from inflation and partly because Kiewit underestimated the cost of drilled shafts.

Kiewit’s recent history includes a dispute in Maryland after the Francis Scott Key Bridge collapsed in spring 2024. Maryland Gov. Wes Moore removed the company from the second phase of that rebuild in April. In a statement, he called the price and timeline “unreasonably high and therefore unacceptable.”

Oregon and Washington lawmakers expressed concern during a joint meeting on Monday. Rep. Thủy Trần, D-Portland, and Sen. Bruce Starr, R-Dundee, asked program administrators how they plan to hold the contractors accountable. Rep. Ed Orcutt, R-Kalama, co-chair of the committee, noted that a single bidder gives the firm leverage. “If you only have one bidder, they can bid whatever they want,” he said.

The program has already seen its own estimates rise. A 2022 projection placed the cost at up to $7.5 billion. By March of this year, officials announced a new figure near $14.4 billion. Washington Gov. Bob Ferguson said a construction contract will be awarded next year. He expects cars to drive on the new bridge by 2035, a delay of roughly two years from previous targets.

Not all lawmakers shared the concern. Rep. Susan McLain, D-Forest Grove, said in an email that the three firms bring necessary resources and expertise. “There are very few firms in the country that have the capacity or experience needed to take on a project of this size,” she said. Rep. Jake Fey, D-Tacoma, chair of the House Transportation Committee, added that he is not concerned because two interested firms decided to collaborate rather than compete.

More Business · Consumer Alerts · Report a business · Got a Story?

Get Headlines Times in your inboxReporting on the stories people talk about. Free, a few times a week, unsubscribe any time.

Related stories

Get Headlines Times in your inboxReporting on the stories people talk about. Free, a few times a week, unsubscribe any time.